Soft conflicts of BDS-NOV-2025.fet Generated with FET 7.1.7 on 11/11/25 12:09 PM Number of broken soft constraints: 8 Total soft conflicts: 7.4 Soft conflicts list (in decreasing order): Time constraint min days between activities broken: activity with id=165 ( 2/8 - Deepak - MAT - C4) conflicts with activity with id=162 (2/8 - Deepak - MAT - C4), being 1 days too close, on days Sa and Sa, conflicts factor increase=0.95. The activities are placed consecutively in the timetable, because you selected this option in case the activities are on the same day Time constraint min days between activities broken: activity with id=186 ( 1/5 - Reetu,Annu - MAT - L2) conflicts with activity with id=185 ( 2/5 - Reetu,Annu - MAT - L2), being 1 days too close, on days We and We, conflicts factor increase=0.95. The activities are placed consecutively in the timetable, because you selected this option in case the activities are on the same day Time constraint min days between activities broken: activity with id=216 ( 1/5 - Nikita,Annu - PE - BEG) conflicts with activity with id=214 (1/5 - Nikita,Annu - PE - BEG), being 1 days too close, on days Tu and Tu, conflicts factor increase=0.95. The activities are placed consecutively in the timetable, because you selected this option in case the activities are on the same day Time constraint min days between activities broken: activity with id=217 ( 1/5 - Nikita,Annu - PE - BEG) conflicts with activity with id=215 ( 1/5 - Nikita,Annu - PE - BEG), being 1 days too close, on days Mo and Mo, conflicts factor increase=0.95. The activities are placed consecutively in the timetable, because you selected this option in case the activities are on the same day Time constraint min days between activities broken: activity with id=221 ( 1/5 - Nikita,Annu - PE - L1) conflicts with activity with id=220 ( 1/5 - Nikita,Annu - PE - L1), being 1 days too close, on days Tu and Tu, conflicts factor increase=0.95. The activities are placed consecutively in the timetable, because you selected this option in case the activities are on the same day Time constraint min days between activities broken: activity with id=226 ( 1/5 - Nikita - PE - L2) conflicts with activity with id=225 ( 1/5 - Nikita - PE - L2), being 1 days too close, on days Th and Th, conflicts factor increase=0.95. The activities are placed consecutively in the timetable, because you selected this option in case the activities are on the same day Time constraint min days between activities broken: activity with id=14 ( 2/4 - Ashutosh - PE - OG - C7) conflicts with activity with id=13 (2/4 - Ashutosh - PE - OG - C7), being 1 days too close, on days Fr and Sa, conflicts factor increase=0.85. Time constraint min days between activities broken: activity with id=28 ( 2/4 - Nisha - R1 ENG - C7) conflicts with activity with id=27 (2/4 - Nisha - R1 ENG - C7), being 1 days too close, on days Th and Fr, conflicts factor increase=0.85. End of file.